IT project from: custom manufacturer (electrical systems) (Germany)Project no. 21/2495: finished
Are you also looking for software?
Matching software categories:
Ihr Ansprechpartner für diese Recherche
Mr. Dipl.-Ing. Olaf Kram
olaf.kram@softguide.de

We are an electrical engineering company (e.g., transformer stations, cabinet distributors). From planning to the finished connection, our customers receive complete solutions from a single source. To optimize our project-related manufacturing, we are looking for software to monitor production times and capacity planning in production.

The software should meet the following requirements:

  • Mapping of two different number ranges
  • Target/actual comparison (projects, time, employees)
  • Project recording
  • Usable for employee capacity planning
  • Times should be measured per item or manufactured station
  • Production takes place at different production stations with different employees and, in some cases, at the customer's site
  • If possible, also as a replacement for our general time recording solution, then also with hardware (fixed station, e.g., terminal and for field service via mobile device)
  • Interface to the existing SAP solution
  • On-premises or web-based

Approximately 45-60 software workstations are planned. Work will be carried out in an MS Windows system environment.

Based on the specific requirements, the following solutions can be considered:

planeus – Digital Production Planning and Control
Projektron BCS - Web-based project management software
GANTTPLAN APS - optimization-based detailed planning/production control center

Project statistics

Quantity
Researched solutions 31
Selected potentially relevant solutions (of which published) 21 (4)
Sent e-mails (questions, queries) and telephone calls 65
E-mails received from vendors 21
Direct responses to the IT project 8
Responses classified as relevant 13